40 containers from Xi’an to Baku in 23 days
Task
A manufacturer was bringing components by sea through European ports: 45 to 55 days in transit. To keep the assembly line running they had to hold two months of stock, which tied up cash and warehouse space.
Challenge
The middle corridor means three changes of transport and two transshipments, each with its own operator. The Caspian ferry is the bottleneck: the schedule shifts with weather and loading. The previous contractor quoted 20 to 40 days with no commitment.
What we did
We took the whole route on ourselves: rail slots booked a quarter ahead, our own agent in Aktau supervising the ferry loading, receiving in Alat and delivery to our warehouse. Customs was started on preliminary documents before the ferry arrived, so containers never queued at the port. Wagons were unloaded by our own cranes on our own siding.
Result
23 days from the departure station to the warehouse instead of 50 by sea, with no more than two days of variance across six shipments. The client halved its safety stock and moved to regular monthly batches.
Cargo
| Cargo | Components for assembly production |
| Units | 40 × 40'HC containers |
| Net weight | 18.5 t per container, 740 t total |
| Volume | 76 m³ per container, 3,040 m³ total |
| Packing | Crates on pallets, 20 per container |
Route
| Xi’an — Dostyk, container train | 6 days |
| Dostyk — Aktau Port, rail | 9 days |
| Aktau — Alat, Caspian ferry | 3 days |
| Alat — warehouse in Baku, road | 1 day |
| Customs and release | 4 days |